Exam-style question
Try this first
If a company has a budgeted overhead of £50,000 and a budgeted activity level of 10,000 machine hours, what is the overhead absorption rate?.
- A.£5 per machine hour
- B.£10 per machine hour
- C.£2 per machine hour
- D.£15 per machine hour
Answer and explanation
Concise answer
£5 per machine hour
Why this is correct
In this case, £50,000 / 10,000 machine hours = £5 per machine hour, which is used to allocate overhead costs to products.
Use the concise answer above for a quick check, then reveal the full model answer and detailed explanation.
Common mistake
No common mistake is linked to this question yet.