For a project task that is not of A-level standard, which part is excluded from the downward adjustment described in the specification?

Try the question, check the answer, then read the explanation to understand the curriculum point.

At a glance

MCQ

Type

practice

Style

Topic

Project tasks that are not of A-level standard

Exam-style question

Try this first

For a project task that is not of A-level standard, which part is excluded from the downward adjustment described in the specification?.

  1. A.Documented design
  2. B.Evaluation
  3. C.Technical solution
  4. D.Every section equally

Model answer

What a good answer should say

  • Technical solution.

Explanation

Why this works

The adjustment is made in each section for all but the technical solution. Evaluation has a special wording: the adjustment is two marks rather than two marking levels.

Common mistake

No common mistake is linked to this question yet.

Related flashcards

No flashcards are published for this page yet.

Related practice questions

No questions are published for this page yet.