Exam-style question
Try this first
What adjustment is specified for the evaluation section when the project task is below A-level standard?.
- A.Move the result down by two marking levels
- B.Reduce the result by two marks
- C.Award Level Four automatically
- D.Do not assess the evaluation
Model answer
What a good answer should say
- Reduce the result by two marks.
Explanation
Why this works
The requirement distinguishes evaluation from the other sections: the downward adjustment is two marks in the case of evaluation, rather than two marking levels.
Common mistake
No common mistake is linked to this question yet.