Which sequence correctly describes the process for a project task that is not of A-level standard?

Try the question, check the answer, then read the explanation to understand the curriculum point.

At a glance

MCQ

Type

practice

Style

Topic

Project tasks that are not of A-level standard

Exam-style question

Try this first

Which sequence correctly describes the process for a project task that is not of A-level standard?.

  1. A.Ignore the criteria, then award marks using personal judgement
  2. B.Apply the criteria, then adjust the relevant award downwards as specified
  3. C.Adjust the technical solution first, then assess all other sections normally
  4. D.Award the highest level first and reduce it only if the project is incomplete

Model answer

What a good answer should say

  • Apply the criteria, then adjust the relevant award downwards as specified.

Explanation

Why this works

The standard should first be taken into account by directly applying the criteria. For a task below A-level standard, the resulting award is then shifted down by two levels in the relevant sections, with evaluation reduced by two marks and the technical solution excluded from the adjustment.

Common mistake

No common mistake is linked to this question yet.

Related flashcards

No flashcards are published for this page yet.

Related practice questions

No questions are published for this page yet.