What adjustment is necessary for work in progress?

Try the question first, then check the answer and practise the same topic again.

At a glance

MCQ

Type

cambridge_mcq

Style

Topic

Manufacturing accounts

Exam-style question

Try this first

What adjustment is necessary for work in progress?.

  1. A.Add to total factory cost
  2. B.Subtract from total factory cost
  3. C.No adjustment needed
  4. D.Include in direct materials

Answer and explanation

Concise answer

Add to total factory cost

Why this is correct

This adjustment ensures that all costs incurred on unfinished goods are accounted for in the total factory cost.