Exam-style question
Try this first
Calculate the time required to machine a part if the cutting speed is 150 mm/min and the total length of the cut is 600 mm.
Answer and explanation
Concise answer
The time required to machine the part is 4 minutes.
Why this is correct
Time = Total Length / Cutting Speed = 600 mm / 150 mm/min = 4 minutes.
Use the concise answer above for a quick check, then reveal the full model answer and detailed explanation.
Common mistake
No common mistake is linked to this question yet.